Project Updates 2022

October 2022

Site

Investigation

As promised through all stages of pre-planning, the Bracklyn wind farm team are keeping the community informed of the ongoing plan for the development.

The team wish to advise you of our intention to commence site investigation works in November/ December 22.

Site investigation works will mainly include soil sampling and rotary cores.  You may see an excavator and drilling rig working on site for a period of 4-6 weeks. Bracklyn Wind Farm want to point out the upcoming site investigation works is not the commencement of construction of the wind farm.   

Should you have any questions on this please email us on clo@bracklynwindfarm.ie or call 1800 140976

August 2022

Post planning community engagement

Screenshot 2022-08-08 at 20.47.08.png

Any questions?

 

Send us an email:

 

clo@bracklynwindfarm.ie

or  call us on 1800 140 976

July 2022

Post planning community engagement

Screenshot 2022-07-28 at 20.27.29.png

July 2022

Planning 

Application

Bracklyn Wind Farm has received correspondence today, 11th July 2022, from An Bord Pleanala regarding the application.

We received notice of a grant of planning for Bracklyn Wind Farm

https://www.pleanala.ie/en-ie/case/311565

June 2022

Planning 

Application

Bracklyn Wind Farm has received correspondence today, 29th June 2022, from An Bord Pleanala regarding the application.

May 2022

Planning 

Application

Bracklyn Wind Farm has received correspondence today, 17th May 2022, from An Bord Pleanala regarding the application.

A new decision date of 27th June 2022 has been allocated to this application.

JANUARY 2022

Metmast

Bracklyn Wind Farm plan to extend the met mast that is currently on site in Q1 2022 depending on suitable weather conditions.

The current met mast is at 80 meters height. This will be extended with an additional 20 meters and an aviation light as in agreement with obtained planning.

bottom of page